Example: Gantt Chart Table

Below is an example of a Gantt Chart table with 100 activities for a simple project, such as the construction of a small building. The activities are broken down into different phases, each with several tasks. The tasks are listed sequentially, and durations are assigned to each task.

Task Name                                Duration  Start Date  Finish Date
------------------------------------------------------------------------
1. Project Initiation                    5 days    01/01/2024  01/05/2024
   1.1 Project Kickoff Meeting           1 day     01/01/2024  01/01/2024
   1.2 Site Selection                    3 days    01/02/2024  01/04/2024
   1.3 Permits and Approvals             1 day     01/05/2024  01/05/2024

2. Design Phase                          20 days   01/06/2024  01/25/2024
   2.1 Architectural Design              5 days    01/06/2024  01/10/2024
   2.2 Structural Design                 7 days    01/11/2024  01/17/2024
   2.3 Electrical and Plumbing Design    5 days    01/18/2024  01/22/2024
   2.4 Design Approval                   3 days    01/23/2024  01/25/2024

3. Site Preparation                      10 days   01/26/2024  02/08/2024
   3.1 Site Clearing                     4 days    01/26/2024  01/29/2024
   3.2 Excavation                        6 days    01/30/2024  02/04/2024
   3.3 Surveying and Grading             3 days    02/05/2024  02/07/2024

4. Foundation                           15 days   02/09/2024  02/23/2024
   4.1 Pour Concrete Footings            5 days    02/09/2024  02/13/2024
   4.2 Install Reinforcement Bars        4 days    02/14/2024  02/17/2024
   4.3 Pour Slab Foundation             6 days    02/18/2024  02/23/2024

5. Structural Work                       25 days   02/24/2024  03/29/2024
   5.1 Build Steel Framework             7 days    02/24/2024  03/01/2024
   5.2 Install Floor Slabs               6 days    03/02/2024  03/07/2024
   5.3 Construct External Walls          8 days    03/08/2024  03/15/2024
   5.4 Install Roof Structure            4 days    03/16/2024  03/19/2024

6. Electrical and Plumbing               20 days   03/20/2024  04/08/2024
   6.1 Install Electrical Wiring          8 days    03/20/2024  03/27/2024
   6.2 Install Plumbing Pipes            6 days    03/28/2024  04/02/2024
   6.3 Install HVAC System               6 days    04/03/2024  04/08/2024

7. Interior Work                         15 days   04/09/2024  04/23/2024
   7.1 Install Windows and Doors         5 days    04/09/2024  04/13/2024
   7.2 Interior Walls and Partitioning   5 days    04/14/2024  04/18/2024
   7.3 Install Flooring                  3 days    04/19/2024  04/21/2024
   7.4 Install Ceiling                    2 days    04/22/2024  04/23/2024

8. Exterior Work                         10 days   04/24/2024  05/07/2024
   8.1 Install Facade                    4 days    04/24/2024  04/27/2024
   8.2 Exterior Painting and Finishing   3 days    04/28/2024  04/30/2024
   8.3 Landscaping                       3 days    05/01/2024  05/03/2024
   8.4 Driveway and Parking Lot          2 days    05/04/2024  05/07/2024

9. Final Inspection and Handover         5 days    05/08/2024  05/12/2024
   9.1 Final Inspection                  2 days    05/08/2024  05/09/2024
   9.2 Resolve Punch List Items          2 days    05/10/2024  05/11/2024
   9.3 Handover to Client                1 day     05/12/2024  05/12/2024
    

Work Resources

Resource Name                    Type        Standard Rate
---------------------------------------------------------
1. Project Manager               Work        $50/hour
2. Architect                     Work        $40/hour
3. Civil Engineer                Work        $45/hour
4. Structural Engineer           Work        $42/hour
5. Laborer                       Work        $25/hour
6. Electrician                   Work        $30/hour
7. Plumber                       Work        $28/hour
8. HVAC Technician               Work        $35/hour
9. Construction Foreman          Work        $38/hour
10. Site Surveyor                Work        $40/hour
    

Material Resources

Resource Name                    Type        Standard Rate
---------------------------------------------------------
1. Concrete                      Material    $100/cubic yard
2. Steel Beams                    Material    $500/ton
3. Lumber                         Material    $200/1000 feet
4. Plumbing Pipes                 Material    $50/foot
5. Electrical Wiring               Material    $2/foot
6. HVAC Units                     Material    $1,500/unit
7. Cement                          Material    $75/bag
8. Insulation                     Material    $80/square foot
9. Windows                        Material    $150/window
10. Paint                          Material    $50/gallon
    

Cost Resources

Resource Name                    Type        Standard Rate
---------------------------------------------------------
1. Permits and Approvals          Cost        $5,000
2. Site Preparation Contractor    Cost        $10,000
3. Waste Removal Service          Cost        $2,000
4. Equipment Rental               Cost        $1,500/day
5. Inspection Fees                Cost        $3,000
6. Legal Services                 Cost        $150/hour
7. Insurance                      Cost        $10,000
8. Miscellaneous                  Cost        $500
9. Safety Equipment               Cost        $1,000
10. Temporary Facilities          Cost        $2,500
    

Assigning Resources to Tasks

Once the resources have been defined in the "Resource Sheet" view, you can assign them to tasks in the Gantt Chart. For example:

  • The "Project Manager" could be assigned to the "Project Kickoff Meeting" task.
  • The "Laborers" could be assigned to the "Site Clearing" and "Excavation" tasks.
  • Material resources like "Concrete" can be assigned to the "Pour Concrete Footings" and "Pour Slab Foundation" tasks.
  • Equipment rental costs could be applied to tasks involving machinery or heavy equipment.

Example: Resource Allocation for the "Site Preparation" Phase

Below is an example of how resources could be allocated to tasks in the "Site Preparation" phase:

Task Name                      Assigned Resources
---------------------------------------------------------
Site Clearing                   Laborer (5 workers), Excavator (1 machine), Concrete (10 cubic yards)
Excavation                      Laborer (6 workers), Excavator (2 machines), Concrete (5 cubic yards)
Surveying and Grading           Site Surveyor (1 worker), Bulldozer (1 machine)
    